CUB was contracted by Core Project Group Pty Ltd to complete the full strip out of all 12 levels, friable asbestos removal from all levels and remove 300mmm thick concrete roof structure of the very first 5 star hotel to come to Newcastle.
This involved encapsulating the full core section of the building while completing all friable asbestos removal, some detailed thought-out methodologies where designed to prop flooring and complete the demolition of the roof section with the right weights and equipment for the task.
We also used a small demolition robot to complete crush down 300mm slab section while we could only have two 2 tonne bins to load out and remove from roof by crane.
Other equipment for this project including a 1.6 tonne excavator, PT60 posi track, Husqvarna demolition robot, and a 60 tonne crane.